New Business Park Cable Duct Installation

Traveling Far and wide, to the heel of the country this week for Mole Group Utilities. Mid way through development with a new business park, there was the requirement for some electric ducting to be drilled across the site road.

We were approached by construction company Guildcrest Homes with a very specific date in mind for their installation to coincide with the electric boards date to connect.

Mole Utilities were happy to oblige arranging a site survey to outline to site requirements. Following thorough site survey the date was confirmed and Mole Utilities arranged a GPR Scan to locate any potential obstacles.  Working with this prestige client on appropriate below ground routes we used our HDD technology to directionally drill the required ducts.

Following the review of the scan, the works took place, with the successful installation of 2no 160mmOD MDPE black ducts under the road and ready for connection by the electric board. This is what we do: enable vital connections of utilities!

Previous
Previous

Solar Cabling at Petroleum Storage Depot, Bristol

Next
Next

The First Frost at Frontier Park